Due to previously unknown federal permit requirements we will be unable to make a vehicle crossing of the river to provide transport for volunteer workers and equipment. The lead time for receiving one of the fisheries permits is 30-45 days minimum, six months possible. By the start of October we are likely to see the Forest Service hazmat closure begin and the water level rising.
We are reassessing our situation, hoping to have both group and individual opportunities to take down and store interpretive signs and cut brush prior to the start of the exclusion, which is likely to keep people out until at least the start of summer 2015.
Check in soon for more information!