We had another productive work party August 18. Our biggest task of re-roofing FS cabin #3 is precisely 50% done; we plan to complete the second half at the September 15 work party; we also found a couple broken rafters on the opposite side of the roof which will need repair too.
Other work accomplished included white trim painted on Cabins 1 and 2, brushcutting up the glacier basin trail, and improving the accessibility of the monte cristo road/trail at the entrance to the clayslide.
See the photo album below showing the before, during and after condition of Cabin #3 roof.